Punch Lists in Florida Construction
A punch list itemizes work to complete/correct before project completion. Created during walk-through. Owner may withhold 150% of estimated completion cost (Section 713.346). Contractor: 30 days to complete. If not: owner hires another contractor, deducts from withheld funds. Disputes: scope vs. change orders, quality, timing, and cost withholding.
Contents
- Cosmetic defects, incomplete work
- Code violations
- Specific, agreed, time-bound
Payment
- Withhold 150% of completion cost
- 30 days to complete (Section 713.346)
- Owner can hire replacement if not done
Disputes
- Scope: punch list vs. change order
- Quality: contract specifications
- Refer to contract and building code
Related Terms
- Construction Lien — Lien rights
Barnes Walker Construction Law
Barnes Walker’s attorneys handle construction disputes in Florida. Request a legal inquiry for assistance.
Reviewed by the attorneys at Barnes Walker, Goethe, Shea & Robinson, PLLC